You are loading in a port subject to the tropical load line mark and bound for a port subject to the summer load line mark. You will enter the summer zone after steaming ten days. You will consume 33 tons of fuel, water, and stores per day. The hydrometer reading at the loading pier is 1.021, and the average TPI is 51. What is the minimum freeboard required at the start of the voyage? Reference Table BL-0017 below.
You are loading in a port subject to the tropical load line mark and bound for a port subject to the summer load line mark. You will enter the summer zone after steaming ten days. You will consume 33 tons of fuel, water, and stores per day. The hydrometer reading at the loading pier is 1.021, and the average TPI is 51. What is the minimum freeboard required at the start of the voyage? Reference Table BL-0017 below.