When securing a main propulsion turbine equipped with carbon packing glands, the vacuum should always be broken before securing the gland seal steam because __________.
A
loop seal will flood the aftercondenser
B
gland seal leakoff lines will flood with water
C
cold air rapidly entering the gland may result in damage to the carbon segments and sealing surfaces
D
the turbine rotor expands faster than the gland casing