The DEEP DRILLER is loaded as shown in Sample Load Form #4 (Drilling). What would be the new sum of vertical moments for the Stores & Supplies if paint weighing 3.48 tons is added to the paint locker?
A
13,346 foot-tons
B
5,054 foot-tons
C
964 foot-tons
D
292 foot-tons