Multiple grounds have developed and were initially indicated by the ground-detecting system as one ground. What is the FIRST step in locating the grounds?
A
examine the main bus bars for signs of overheating
B
eliminate the individual circuits one by one until the ground detecting system no longer indicates any grounds
C
change over generators
D
check each circuit with a megohmmeter