For newly constructed vessels, extensive shipyard repair or a vessel's modification period, what does a shipyard's 'Gantt' chart represent?
Daily shipyard's production figures and progress.
Project's shipyard fiscal and man-hours expenditures per item/goal.
Daily actual shipyard progress, per item, vs. estimated.
Master schedule of time/man-hours vs. project's significant goals/items for the duration of the project.