As it pertains to task scheduling in project management, what statement is true concerning the critical path?
A
The critical path is that particular path of relationally dependent tasks which requires the most in manpower resources and as such that identifies the path with the highest man-hour requirements.
B
The critical path is that particular path of relationally dependent tasks which requires the most time and as such determines the overall length of the project.
C
The critical path is that particular path of relationally dependent tasks which requires the most in financial resources and as such that identifies the path with the highest budget items.
D
The critical path is that particular path of tasks with no dependencies which requires the least time and as such determines the overall length of the project.