As it pertains to graphical tools used to visualize task scheduling in project management, what statement best represents the difference between a Gantt chart and a PERT chart?
A
The PERT chart (which is a line diagram) makes it easy to visualize task dependencies and milestones, whereas the Gantt chart (which is a bar chart) makes it easy to visualize progress with respect to an actual calendar.
B
The Gantt chart makes it easy to visualize task dependencies and milestones, whereas the PERT chart makes it easy to visualize progress with respect to an actual calendar. Both are line diagrams.
C
The PERT chart (which is a bar chart) makes it easy to visualize task dependencies and milestones, whereas the Gantt chart (which is a line diagram) makes it easy to visualize progress with respect to an actual calendar.
Question 1 / 2066636eee28f7522a1c51ef5e
Question 1 of 2066636eee28f7522a1c51ef5e
As it pertains to graphical tools used to visualize task scheduling in project management, what statement best represents the difference between a Gantt chart and a PERT chart?
As it pertains to graphical tools used to visualize task scheduling in project management, what statement best represents the difference between a Gantt chart and a PERT chart?
No comments yet
Be the first to share your thoughts!
D
The Gantt chart makes it easy to visualize task dependencies and milestones, whereas the PERT chart makes it easy to visualize progress with respect to an actual calendar. Both are bar charts.