A charterer is unable to complete the loading of a vessel during the lay days specified in the charter party. Under these circumstances, which action may occur?
β’ Lay days / laytime in a charter party and what they represent β’ Difference between demurrage and dispatch money β’ What happens when loading or discharging is slower or faster than agreed
β’ Think about whether the charterer used more or less time than allowed for loading the vessel β’ Ask yourself: is the charterer causing a delay to the ship, or saving time for the ship? β’ Consider which payments are made to compensate the vessel operator for delay versus reward the charterer for saving time
β’ Determine if the situation describes exceeding the agreed lay days or finishing early β’ Recall which term applies when extra time beyond lay days is used for cargo operations β’ Verify which payment (dispatch or demurrage) goes to the charterer and which goes to the vessel operator